Work to begin on U.S. 218 in Iowa

Published 12:00 am Thursday, May 3, 2007

Construction on U.S. Highway 218 is expected to begin today. The construction zone stretches from just north of Saint Ansgar, Iowa, to the Minnesota state line.

This project includes full-lane-width patching and slurry seal in the wheel paths. The patching will begin next week and take one week to complete. Slurry seal will not begin until mid-July and expected to last one week.

When construction work is being performed on the roadway, pilot cars and flaggers will be used to maintain traffic.

Email newsletter signup

Short-term delays can be anticipated while traveling through this construction area. All items on this project are expected to be completed by late July.