MnDOT construction projects for 2010
Published 10:30 am Friday, April 9, 2010
The listing below is the Minnesota Department of Transportation construction projects for the Rochester and Mankato districts.
District 6
Rochester/Owatonna/Winona
District 7
Location: Hwy 13 – I-90 to Hwy 30
Description: Mill and bituminous overlay
Construction dates: July to September 2010
Construction cost: $4 million
Impacts: Daily lane closures with flaggers, short-term detour
Location: Hwy 14 – Hwy 52 to Marion Road
Description: Mill and bituminous overlay, improve intersection and traffic signals, improve intersections, bike path addition
Construction dates: June to October 2010
Construction cost: $4.7 million; $3.2 million (MnDOT share)
Impacts: Long-term lane closures
www.dot.state.mn.us/d6/projects/hwy14inrochester/
Location: Hwy 16 – Houston to Hokah
Description: Resurface road
Construction dates: June to August 2010
Construction Cost: $4.4 million
Impacts: Road closure, detour, flaggers
Location: Hwy 19 – Hwy 13 to 3rd Ave SE in Lonsdale and I-35 SB ramps to Armstrong Road in Northfield
Description: Mill and bituminous overlay
Construction dates: July to September 2010
Construction cost: $6.5 million
Impacts: Daily lane closures with flaggers, detours
Location: I-35 – southbound lanes from Steele CR 31 to Hwy 30
Description: Bituminous mill and overlay
Construction dates: May to July 2010
Construction cost: $3.7 million
Impacts: Lane closures, head-to-head traffic on NB lanes, SB ramps at Steele CR 4/Hope interchange closed
Location: Hwy 43 – Hwy 44 to Hwy 16
Description: Mill and bituminous overlay, preventive maintenance
Construction dates: July to October 2010
Construction cost: $1.45 million
Impacts: Daily lane closures with flaggers
Location: Hwy 52 – Willow Creek and Olmsted CR 1
Description: Reconstruct bridges, overlay the bridge deck
Construction dates: June to October 2010
Construction cost: $1.9 million
Impacts: Long-term lane closures
Location: Hwy 52
Description: Improve intersection and manage access for safety improvements
Construction Dates: August to September 2010
Construction Cost: $389,130
Impacts: Intermittent lane closures
Location: Hwy 52 – Goodhue CR 24
Description: Continue environmental assessment, begin right of way acquisition for mobility and safety improvements
Construction dates: TBD
Construction cost: $1.8 million
Impacts: No Impacts
Location: Hwy 56 – Brownsdale to Dodge CR 10
Description: Mill and bituminous overlay
Construction dates: May to August 2010
Construction cost: $6 million
Impacts: Daily lane closures, flaggers, short-term detour
Location: Hwy 56 – Dodge CR 34 to West Concord
Description: Resurface with concrete
Construction dates: June to August 2010
Construction cost: $2.9 million
Impacts: Road closure, detour
Location: Hwy 58 – Goodhue County
Description: Replace bridge and box culvert over Zumbro River in Zumbrota
Construction dates: June to September 2010
Construction cost: $1.4 million
Impacts: Bridge closure, detour
Location: Hwy 60 – Hwy 13 to Hwy 21 in Waterville and Faribault
Description: Mill and bituminous overlay
Construction dates: August to September 2010
Construction cost: $3.5 million
Impacts: Daily lane closures, flaggers
Location: Hwy 61 – Winona CR 15 to Hwy 14 in Homer and Winona
Description: Mill and bituminous overlay
Construction dates: July to September 2010
Construction cost: $2.7 million
Impacts: Intermittent lane closures
Location: Hwy 61 – Lake City
Description: Replace historic walls along Hwy 61 as part of the Great River Road Historic Property Restoration
Construction dates: June 7 to Aug. 27, 2010
Construction cost: $1 million
Impacts: TBD
Location: Hwy 63 – 6th St intersection in Stewartville
Description: Improve intersection safety, modify traffic signals
Construction dates: September to October 2010
Construction cost: $362,000
Impacts: Minimal
Location: Hwy 74 – Chatfield to St. Charles
Description: Mill and bituminous overlay, improve accessibility
Construction Dates: July to September 2010
Construction Cost: $3.5 million
Impacts: Daily lane closures with flaggers
Location: I-90 – Hwy 74 to Hwy 43
Description: Resurface eastbound lanes with concrete
Construction dates: May to November 2010
Construction cost: $15.3 million
Impacts: Long-term lane closures, head-to-head traffic CR 29/Lewiston interchange closure, Enterprise Rest Area closure
Location: I-90 – Mower CR 19 to Hwy 16
Description: Repair concrete pavement, replace bituminous shoulder for preventive maintenance
Construction dates: July to September 2010
Construction cost: $1.9 million
Impacts: Long-term lane closures
Location: Hwy 105 – Mower County just north of the Iowa border
Description: Replace Woodbury Creek bridge
Construction dates: May to August 2010
Construction cost: $621,677
Impacts: Bridge closure, detour
Location: Hwy 218 – Mower County
Description: Install railroad crossing gates
Construction dates: Expected completion September 2010
Construction cost: $196,000
Impacts: Daily lane closures, flaggers
Location: Hwy 250 – Hwy 16 to Hwy 30
Description: Mill and bituminous overlay
Construction dates: July – October 2010
Construction cost: $640,000
Impacts: Daily lane closures, flaggers
Location: Various highways – Goodhue, Winona, Olmsted, Fillmore, Freeborn, Houston and Steele counties
Description: Install curve signing on 50 curves
Construction dates: April to May 2010
Construction Cost: $56,578
Impacts: Minimal
Location: Various highways – Goodhue, Mower, Rice, Winona and Olmsted counties
Description: Install lights at eight rural intersections
Construction dates: April to May 2010
Construction cost: $104,661
Impacts: Minimal
Location: Various highways – Dodge, Goodhue, Steele and Winona counties
Description: Upgrade 247 signs
Construction dates: April to May 2010
Construction cost: $80,950
Impacts: Minimal
Location: Various highways – Rice, Winona and Olmsted counties
Description: Install pedestrian ramps for accessibility
Construction Dates: June to August 2010
Construction Cost: $667,000
Impacts: Intermittent lane closures
Location: Various highways – Freeborn County
Description: Install pedestrian ramps for accessibility
Construction dates: September 2010
Construction cost: $165,825
Impacts: Intermittent lane closures
Location: Various highways – Rice, Winona, Mower, Steele, Houston, Goodhue, Olmsted and Fillmore counties
Description: Rout and seal bituminous pavement cracks
Construction dates: 2010
Construction cost: $214,000
Impacts: Daily lane closures, flaggers
Location: Hwy 52 – Olmsted and Goodhue counties
Description: Construct interchange and frontage road near Pine Island
Construction dates: 2010 to 2012
Construction cost: $30 million
Impacts: Temporary lane closures, head-to-head traffic, local Impacts
www.dot.state.mn.us/d6/projects/hwy52pineisland/
Location: I-90 in Mower County
Description: Replace four bridges (Dobbins Creek; EB and WB bridges on I-90 over Turtle
Creek; I-90 overpass under the WB off-ramp near the jct of Hwy 218 in Austin)
Construction cost: $8.06 million
Construction dates: March to September 2010
Impacts: Head-to-head traffic on alternating sides of I-90 closures (Dobbins Creek Area), head-to-head traffic, detour (Turtle Creek Area) www.dot.state.mn.us/d6/projects/bridges_of_mower_county/
Location: Hwy 14 – Waseca CR 5 to Steele CR 7
Description: Grade and surface, construct I-35/Hwy 14 interchange
Construction Dates: July 2009 to 2012
Construction cost: $51.7 million
Impacts: Long-term lane closures, head-to-head traffic, traffic delays, intermittent lane closures
Location: I-90 – Winona County
Description: Replace four bridges at Dresbach Township
Construction dates: May 2009 to November 2010
Construction cost: $4.4 million
Impacts: Long-term lane closures, head-to-head traffic
District 7
Mankato//Windom
Location: Hwy 13 – Hwy 30 to Waseca CR 8
Description: Mill and overlay
Construction dates: August 2010
Construction cost: $130,000
Impacts: Brief delays, flaggers
Location: Hwy 14 – Sleepy Eye
Description: Repair concrete pavement
Construction Dates: June 2010
Construction Cost: $50,000
Impacts: Brief delays, flaggers
Location: Hwy 14 – Waseca
Description: Mill and overlay
Construction dates: August 2010
Construction cost: $230,000
Impacts: Brief delays, flaggers
Location: Hwy 14 – Waseca
Description: Construct four lanes on new alignment south of Waseca, 10 bridges
Construction dates: 2008 to 2011/2012
Construction cost: $56 million
Impacts: Two-month detour to old Hwy 14 www.dot.state.mn.us/d7/projects/14owatonna/
Location: Hwy 14/15
Description: Install audible signal and pedestrian ramp upgrades
Construction dates: June 2010
Construction Cost: $175,826
Impacts: Brief delays
Location: Hwy 15 – Truman to Hwy 60
Description: Repair shoulder
Construction dates: August 2010
Construction Cost: $200,000
Impacts: Brief delays, flaggers
Location: Hwy 15 – New Ulm to Winthrop
Description: Repair pavement
Construction dates: July 2010
Construction cost: $580,000
Impacts: Brief delays, flaggers
Location: Hwy 22/111 – Nicollet to Nicollet CR 1
Description: Pave shoulders, install rumble strips for improved safety
Construction dates: June 2010
Construction cost: $665,000
Impacts: Brief delays, flaggers
Location: Hwy 30 – Mapleton
Description: Grade and surface
Construction Dates: May 2009 to June 2010
Construction Cost: $2.6 million (Mn/DOT share)
Impacts: Brief restrictions
Location: Hwy 59 – Ryan’s Road in Worthington
Description: Realign frontage road for safety improvements
Construction dates: Summer 2010
Construction cost: $1 million (Mn/DOT share)
Impacts: Short-term lane closures
Location: Hwy 59/Hwy 60 – Nobles CR 4 to Paul Ave in Worthington
Description: Construct four-lane highway
Construction dates: July 2010 to fall 2011
Construction cost: $23 million
Impacts: None www.dot.state.mn.us/d7/projects/hwy60/
Location: Hwy 60 – Worthington to Wilder
Construction Dates: July to October 2010
Construction Cost: $6.2 million
Impacts: Cross-over, reduced lanes
Location: Hwy 62 – Fulda to Windom
Description: Repair pavement
Construction Dates: July 2010
Construction Cost: $200,000
Impacts: Brief delays, flaggers
Location: Hwy 66 – South of Blue Earth CR 90
Description: Repair slope
Construction Dates: August 2010
Construction Cost: $100,000
Impacts: Detour to local roads
Location: Hwy 71 – Bridge over Des Moines River at Windom
Description: Replace bridge
Construction Dates: July to October 2010
Construction Cost: $1.5 million
Impacts: Detour to local roads
Location: I-90 – prairie plantings
Description: Restore prairie on roadsides and in rest areas west of Blue Earth
Construction Dates: 2009 to 2011
Construction Cost: $260,000
Impacts: Minimal
Location: I-90 rest areas – prairie plantings
Description: Plant and maintain prairie wildflowers and grasses at Adrian and Jackson rest areas
Construction dates: September 2010 to 2012
Construction cost: $320,000
Impacts: Minimal
Location: I-90 – Adrian to Rushmore
Description: Repair EB Lanes
Construction dates: June 2010
Construction estimate: $448,000
Impacts: Lane restrictions
Location: Hwy 169 – St. Peter
Description: Construct sidewalks, landscape
Construction dates: May to June 2010
Impacts: Intermittent lane restrictions www.dot.state.mn.us/d7/projects/169stpeter/
Location: Various locations – safety projects
Description: Install rumble stripes, epoxy fog lines and pavement messages
Construction dates: May to August 2010
Construction cost: $500,000
Impacts: Minimal